![]() |
|
![]() |
|
|
|
|
|
pipingdesigners.com Training Seminar
Section - II
A: General Guidelines for Equipment and Piping Location, Spacing, Distances
and Clearances
By: James O. Pennock
This article should only be used as a guide. It's intended purpose is to help the piping designer who is responsible for placement of one specific item in a typical refinery, chemical or petrochemical process plant or someone who may need help in developing a total plot plan for a complex unit.
The guidelines given here are based on my many years of experience with one of the world's largest engineering, design and construction companies along with the U. S. OSHA Part 1910 and the NFPA (National Fire Protection Association) Code No. 30.
The latest editions of these codes and any other applicable national, regional and local codes should be referred to and used because they may be more stringent.
The subjects covered in this article have been arranged in alphabetical order in the hope it will make them easier to locate.
Access (See Maintenance)
Columns (See Vertical Vessels)
Compressors, Centrifugal
Locate centrifugal compressor as close as possible the suction source. Top
suction and discharge lines either should be routed to provide clearance
for overhead maintenance requirements, or should be made up with removable
spool pieces.
Support piping so as to minimize dead load on compressor nozzles; the load
should be within the recommended allowance of the compressor manufacturer.
Centrifugal compressors should have full platforming at operating level.
Heavy parts such as upper or inner casing and rotor should be accessible
to mobile equipment. Review the equipment arrangement for access and operation.
Locate lube and seal oil consoles adjacent to and as close as possible to
the compressor. Oil return lines from the compressor and driver should have
a minimum slope of 1/2 inch per foot to the inlet connection of seal traps,
degassing tanks, and oil reservoir. Pipe the reservoir, compressor bearing,
and seal oil vents to a safe location at least 6 feet above operator head
level.
Compressors, Reciprocating
Locate reciprocating compressors so suction and discharge lines that are
subject to vibration (mechanical and acoustical) may be routed at grade
and held down at points established by a stress and analog study of the
system.
Accessibility and maintenance for large lifts such as cylinder, motor rotor,
and piston removal should be by mobile equipment if the installation is
outdoors or by traveling overhead crane if the installation is indoors (or
covered).
Horizontal, straight line, reciprocating compressors should have access
to cylinder valves. Access should be from grade or platform if required.
Depending on unit size and installation height, horizontal-opposed and gas
engine driven reciprocating compressors may require full platforming at
the operating level.
Control Valves
Locate control valve stations accessible from grade or on a platform. In
general, the (flow, level, pressure, temperature) instruments or indicators
showing the process variables should be visible from the control valve.
Cooling Towers
Locate cooling towers downwind of buildings and equipment to keep spray
from falling on them. Orient the short side of the tower into the prevailing
summer wind for maximum efficiency. This means that the air flow (wind)
will travel up the long sides and be drawn in to both sides of the cooling
tower equally. When the wind is allowed to blow directly into one long side
it tends to blow straight through and results in lower efficiency. Locate
cooling towers a minimum of 100 feet (30m) from process units, utility units,
fired equipment, and process equipment.
Cradles (See Insulation Shoes and Cradles)
Equipment Arrangement (General)
Arrange equipment, structures, and piping to permit maintenance and service
by means of mobile equipment. Provide permanent facilities where maintenance
by mobile equipment is impractical.
Group offsite equipment, pumps, and exchangers to permit economical pipe
routing. Locate this equipment outside of diked storage areas.
Exchanger, Air Cooler (Fin
Fans)
Air Coolers are in typically used in the cooling of the overhead vapor from
tall vertical vessels or towers such as Crude Fractionators and Stripper
Columns. The natural flow tends to follow gravity, where the tower overhead
is the high point then down to the Air Cooler, then down to the Accumulator
and finally the Overhead Product transfer pumps. With this in mind the Air
Coolers are normally located above pipeways. This conserves plot space and
allows the pipe rack structure with it's foundation to do double duty with
only minor up grade to the design. If the pipe rack is not used then plot
space equal to the size of the Air Cooler is required. In addition a totally
separate foundation and stand alone structure is required.
Exchanger, "G"
Fin (Double Pipe)
These exchangers can be mounted almost anywhere any they can be mounted
(with process engineer approval) in the vertical when required. A G-Fin
Exchanger is recognizable by its shape. One segment looks like two long
pieces of pipe with a 180 degree return bend at the far end. It is one finned
pipe inside of another pipe with two movable supports. This type of exchanger
can be joined together very simply to form multiples in series, in parallel
or in a combination of series/parallel to meet the requirements of the process.
This exchanger is not normally used in a service where there is a large
flow rate or where high heat transfer is required. The key feature with
this exchanger is the maintenance. The piping is disconnected from the tube
side (inner pipe). On the return bend end of this exchanger there is a removable
cover. When the cover is removed this allows for the tube (inside pipe)
to be pulled out. This exchanger is normally installed with the piping connections
toward the pipe rack.
Exchangers, Reboiler (Kettle Reboiler)
Locate kettle reboilers at grade and as close as possible to the vessel
they serve. This type of reboiler is identifiable by its unique shape. It
has one end much like a normal Shell and Tube exchanger then a very large
eccentric, bottom flat transition to what looks like a normal horizontal
vessel. You could also call it a "Fat" exchanger. The flow characteristics
on the process side of a kettle reboiler are the reason for the requirement
for the close relationship to the related vessel.
Reboilers normally have a removable tube bundle and should have maintenance
clearance equal to the bundle length plus 5 feet (1.5m) measured from the
tube sheet.
Exchangers, Shell and Tube
Shell and tube exchangers should be grouped together wherever possible.
Stacked shell and tube exchangers should be limited to four shells high
in similar service; however, the top exchanger should not exceed a centerline
elevation of 18 feet (5.5m) above high point of finished surface, unless
mounted in a structure. Keep channel end and shell covers clear of obstructions
such as piping and structural members to allow unbolting of exchanger flanges,
and removal of heads and tube bundles.
Exchangers with removable tube bundles should have maintenance clearance
equal to the bundle length plus 5 feet (1.5m) measured from the tube sheet
to allow for the tube bundle and the tube puller.
Maintenance space between flanges of exchangers or other equipment arranged
in pairs should be 1'- 6" (0.5m) (min.). Exchanger maintenance space
from a structural member or pipe should not be less than 1'- 0" (300mm)
(min.).
Furnaces (Fired Equipment)
Locate fired equipment, if practical, so that flammable gases from hydrocarbon
and other processing areas cannot be blown into the open flames by prevailing
winds.
Horizontal clearance from hydrocarbon equipment (shell to shell) 50'- 0"
(15m) Exception: Reactors or equipment in alloy
systems should be located for economical piping arrangement.
Provide sufficient access and clearance at fired equipment for removal of
tubes, soot blowers, air preheater baskets, burners, fans, and other related
serviceable equipment.
Clearance from edge of roads to shell 10'- 0"(3m)
Pressure relief doors and tube access doors should be free from obstructions.
Orient pressure relief doors so as not to blow into adjacent equipment.
The elevation of the bottom of the heater above the high point of the finished
surface should allow free passage for operation and maintenance.
Furnace Piping
Locate snuffing steam manifolds and fuel gas shutoff valves a minimum of
50 feet (15m) horizontally from the heaters they protect.
Burner Valving for a Floor Fired Furnaces: Combination oil and gas firing
valves should be operable from burner observation door platform. For those
fired by gas only, the valves should be near the burner and should be operable
from grade.
Burner Valving for a Side Fired Furnaces: Locate firing valves so they can
be operated while the flame is viewed from the observation door.
Flare Stacks
Locate the flare stack upwind of process units, with a minimum distance
of 200 feet (60m) from process equipment, tanks, and cooling towers. If
the stack height is less than 75 feet (25m), increase this distance to a
minimum of 300 feet (90m). These minimum distances should be verified by
Company Process Engineering.
Future Provisions
Space for future equipment, pipe, or units should not be provided unless
required by the client or for specific process considerations. When applicable
this requirement should be indicated on the plot plan and P&IDs.
Insulation Shoes and Cradles
Locate Insulation shoes anywhere a line crosses a support for hot insulated
piping when the piping is 3 inch (80mm) and larger carbon and alloy steel
lines with design temperatures over 650 degrees F (350C).
Large diameter lines (20 inches (500mm) and over), stainless steel lines
where galvanic corrosion may exist, lines with wall thickness less than
standard weight, and vacuum lines should be analyzed to determine if shoes
or wear plates are needed.
Provide cradles at supports for insulated lines in cold service and for
acoustical applications.
Ladders & Cages
Maximum height of a ladder without a cage should not exceed 15'-0"
(4.5m)
Maximum vertical distance between platforms 30'- 0" (9m)
Cages on ladders over 15'-0" (4.5m) high shall start at 8'-0"
(2.5m) above grade.
Minimum toe clearance behind a ladder 0'- 7" (200mm)
Minimum handrail clearance 0'- 3" (80mm)
Level Instruments
Locate liquid level controllers and level glasses so as to be accessible
from grade, platform, or permanent ladder. The level glass should be readable
from grade wherever practical.
Wherever possible, orient level instruments on the side toward the operating
aisle.
Loading Racks
Locate loading and unloading facilities that handle flammable commodities
a minimum of 200 feet (60m) from away from process equipment, and 250 feet
(75m) from tankage.
Maintenance Aisles (at
grade)
Equipment maintenance aisle for hydraulic crane (12T capacity) should have
a horizontal clearance width of 10'- 0" (3m) (min.) and a vertical
clearance of 12'- 0" (3.5m) (min.). Where
a fork lift and similar equipment (5000 lbs / 230kg capability) is to be
used the horizontal clearance should be 6'- 0" (2m) (min.) and the
vertical clearance should be 8'- 0" (2.5m) (min.).
Where maintenance by portable manual equipment (A-frames, hand trucks, dollies,
portable ladders or similar equipment) is required the horizontal clearance
should be 3'- 0" (1m) (min.) and the vertical clearance 8'- 0"
(2.5m) (min.).
Operating Aisle (at grade)
Minimum width 2'- 6" (800mm)
Headroom 7'- 0" (2.1m)
Orifice Runs and Flanges
Locate Orifice runs in the horizontal. Vertical orifice runs may only be
used with the approval of Company Control Systems Engineering. Orifice flanges
with a centerline elevation over 15 feet (4.5m) above the high point of
finished surface, except in pipeways, should be accessible from a platform
or permanent ladder.
Locate orifice taps as follows:
Air and Gas
-Top vertical centerline (preferred)
-45 degrees above horizontal centerline (alternate)]
Liquid and Steam
-Horizontal centerline (preferred)
-45 degrees below horizontal centerline (alternate]
(Note: The piping isometrics should show the required tap orientations)
Personnel Protection
Locate eye wash and emergency showers in all areas where operating personnel
are subject to hazardous sprays or spills, such as acid.
Personnel protection should be provided at uninsulated lines and for equipment
operating above 140 degrees F (60 C) when they constitute a hazard to the
operators during the normal operating routine. Lines that are infrequently
used, such as snuffing steam and relief valve discharges, may not require
protective shields or coverings.
Pipe
Clearance between the outside diameter of flange and the outside diameter
of pipe to the insulation should not be less than 0'- 1"* (25mm)
Clearance between the outside diameter of pipe, flange, or insulation and
structural any member should not be less than 0'- 2"* (50mm)
*With full consideration of thermal movements
Platforms
Minimum width for ladder to ladder travel: 2'- 6" (800mm)
Headroom: 7'- 0" (2.1m)
Headroom from stairwell treads: 7'- 0" (2.1m)
Minimum clearance around any obstruction on dead end platforms: 1'- 6"
(500mm)
Pressure Instruments
Locate all local pressure indicators so they are visible from grade, permanent
ladder, or platform. Those located less than 15 feet (4.5m) above high point
of finished surface should be accessible from grade or a portable ladder.
Those located in a pipeway should be considered accessible by portable ladder.
Those over 15 feet (4.5m) above high point of finished surface should be
accessible from a platform or permanent ladder.
Process Units
The relation of units, location of equipment, and routing of pipe should
be based on economics, safety, and ease of maintenance, operation, and construction
requirements. The alignment of equipment and routing of pipe should offer
an organized appearance.
Process Unit Piping
Locate all pipe lines in major process units on overhead pipeways. In certain
instances, pipes may be buried, providing they are adequately protected.
Lines that must be run below grade, and must be periodically inspected or
replaced, should be identified on the P&IDs and placed in covered concrete
trenches.
Cooling water lines normally may be run above or below ground, based on
economics.
Domestic or potable water and fire water lines should be run underground.
Pumps
Locate pumps close to the equipment from which they take suction. Normally,
locate pumps in process units under pipeways.
Design piping to provide clearance for pump or driver removal. Similarly,
on end suction pumps, piping should permit removing suction cover and pump
impeller while the suction and discharge valves are in place.
Arrange suction lines to minimize offsets. The suction lines should be short
and as direct as possible, and should step down from the equipment to the
pump. Suction lines routed on sleeperways may rise to pump suction nozzle
elevation.
Orient valve handwheels or handles so they will not interfere with pump
maintenance or motor removal. Valve handwheels or handles should be readily
operable from grade.
Maintenance and operating aisles with a minimum width of 2'-6" (800mm)
should be provided on three sides of all pumps.
Pump Strainers
Provide temporary conical type strainers in 2 inch (50mm) and larger butt
weld pump suction lines for use during startup. Arrange piping to facilitate
removal.
Use permanent Y-type strainers on 2 inch (50mm) and smaller screwed or socket
weld pump suction piping.
Railroads
Headroom over through-railroads (from top rail) 22'- 6"** (7m)
Clearance from track centerline to obstruction 10'- 0"** (3m)
(** Verify conformance with local regulations)
Relief Valves (Pressure,
Safety and Thermal)
Locate all relief valves so they are accessible. Wherever feasible, locate
them at platforms that are designed for other purposes. Relief valves with
a centerline elevation over 15 feet (4.5m) above high point of finish surface
(except in pipeways) should be accessible from platform or permanent ladder.
Pressure relief valves that discharge to a closed system should be installed
higher than the collection header. There should be no pockets in the discharge
line.
Safety relief valves (in services such as steam, etc.) that discharge to
the atmosphere should have tail pipes extended to a minimum of 8 feet (2.5m)above
the nearest operating platform that is within a radius of 25 feet (7.5m).
This requirement may be waived, provided a review of the proposed arrangement
indicates that it does not present a hazard. Review all pressure and safety
relief valves discharging flammable vapors to the atmosphere within 100
feet (30m) of fired equipment for vapor dissipation.
Pressure and Safety relief valves, 1-1/2 inch (40mm) and larger, should
only be installed with the stem and body vertical position.
Thermal relief valves, 1 inch (25mm) and smaller, may be installed with
the stem and body in a horizontal position when it is impractical to install
it in the vertical position.
Roads
Major process plants normally have three classes of roads. They might be
called Primary roads, Secondary roads and Maintenance access ways.
Clearance or distance required
| Road type | Vertical | Width | Shoulder | Side or off road |
| Primary | 21'-0" (6.5m) | 20'-0" (6m) | 5'-0" (1.5m) | 20'-0" (6m) |
| Secondary (*) | 12'-0" (3.7m) | 12'-0" 3.7m) | 3'-0" (1m) | 10'-0" (3m) |
| Maintenance access | 10'-0" (3m) | 10'-0" (3m) | (not req'd) | 5'-0" (1.5m) |
(*) Normally secondary plant roads may
be used as tube pull areas.
Safety Access
Provide a primary means of egress (continuous and unobstructed way of exit
travel) from any point in any building, elevated equipment, or structure.
A secondary means of escape should be provided where the travel distance
from the furthest point on a platform to an exit exceeds 75 feet (25m).
Access to elevated platforms should be by permanent ladder. Safety cages
should be provided on all ladders over 15'-0" (4.5m)
The need for stairways should be determined by platform elevation, number
of items requiring attention, observation and adjustment, and the frequency
of items.
Ladder safety devices such as cable reel safety belts and harnesses, may
be investigated for use on boiler, flare stack, water tank, and chimney
ladders over 20 feet (6m) in unbroken lengths in lieu of cage protection
and landing platforms.
Sample Connections
Locate all sample connections so they are readily accessible from grade
or platform.
In general, where liquid samples are taken in a bottle, locate the sample
outlet above a drain funnel to permit free running of the liquid before
sampling.
Hot samples should be provided with a cooler.
Sleeper Pipe Supports
Normally, route piping in offsite areas on sleepers. Stagger the sleeper
elevations to permit ease of crossing or change of direction at intersections.
Flat turns may be used when entire sleeper ways change direction.
Spectacle Blinds
Locate spectacle blinds to be accessible from grade or platform. Blinds
located in a pipeway are considered accessible. Blinds that weigh over 100
lbs (45kg) should be accessible by mobile equipment. Where this is not possible,
provide davits or hitching points.
Closely grouped flanges with blinds should be staggered.
Steam Traps
Locate all steam traps at all pocketed low points and at dead ends of steam
headers. Also, provide traps periodically on excessively long runs of steam
piping, for sufficient condensate removal, and to ensure dry quality steam
at destination. Steam traps should be accessible from grade or a platform.
Steam traps located in pipeways should be considered accessible by portable
ladder.
Tankage
Locate any tankage containing hydrocarbon or other combustible fluids or
gasses a minimum distance of 250'-0" (115m) from any process unit,
rail loading facility or truck loading facility.
The minimum spacing of offsite storage tanks and dike requirements should
be in accordance with the latest edition of the National Fire Protection
Association, Code No. 30, and OSHA part 1910.106 (b), where applicable.
Temperature Instruments
Locate temperature test wells, temperature Indicators and thermocouples
to be accessible from grade or a portable ladder. Those located in a pipeway
should be considered accessible by a portable ladder. Those located over
15 feet (7m) above high point of finished surface should be accessible from
a platform or permanent ladder.
Locate all local temperature indicators (TI) should be visible from grade,
ladder, or platform.
Towers (See Vertical Vessel)
Utility Stations
Provide and locate utility stations with water, steam, or air as indicated
below:
All areas should be reachable with a single 50 foot (20m) length of hose
from the station.
Provide water outlets at grade level only, in pump areas, and near equipment
that should be water washed during maintenance.
Provide steam outlets at grade level only in areas subject to product spills,
and near equipment that requires steaming out during maintenance.
Provide air outlets in areas where air-driven tools are used such as at
exchangers, both ends of heaters, compressor area, top platform of reactors,
and on columns at each manway.
Hose, hose rack, and hose connections should be provided by the client or
be purchased to match the clients existing hardware.
Valve Handwheel Clearance
Clearance between the outside of hand wheel and any obstruction (knuckle
clearance) should be 0'- 3" (80mm)
Valve Operation
Locate operating valves requiring attention, observation, or adjustment
during normal plant operation (noted on the P&IDs) so they may be within
easy reach from grade, platform, or permanent ladder as follows:
- 2" (50mm) and smaller may be located reachable from a ladder.
- 3" (80mm) and larger must be reachable and operable on a platform
Operating valves with the bottom of handwheel is over 7 feet (2.1m)above
high point of finished surface or operating platform may be chain-operated.
The centerline of handwheel or handles on block valves used for shutdown
only, located less than 15 feet (4.5m) above high point of finished surface,
and those located in pipeways, may be accessible by portable ladder.
The centerline of handwheel or handles on block valves used for shutdown
only and located over 15 feet (4.5m) above high point of finished surface,
except those located in pipeways, should be operable from permanent ladder
or platform.
In general, keep valve handwheels, handles, and stems out of operating aisles.
Where this is not practical, elevate the valve to 6'- 6" (plus or minus
3 inches) clear from high point of finished surface to bottom of handwheel.
Vents and Drains
The P&IDs should indicate, locate and size all vents, drains, and bleeds
required for process reasons and plant operation.
Provide plugged hydrostatic vents and drains without valves at the high
and low points of piping.
Provide valved bleeds at control valve stations, level switches, level controllers,
and gage glasses per job standard.
Vertical Vessel (Column)
Piping and Platforms
Locate vertical vessels in the equipment rows on each side of the pipeway
in a logical order based on the process and cost. The largest vessel in
each equipment row should be used to set the centerline location of all
vertical vessels in that equipment row. This largest vertical vessel should
be set back from the pipe rack a distance that allows for; any pumps, the
pump piping, an operation aisle between the pump piping and any piping in
front of the vessel, the edge of the vessel foundation and half the diameter
of this the largest vessel. Set all other vertical vessels in this same
equipment row on the same centerline.
Provide a clear access area at grade for vessels with removable internals
or for vessels requiring loading and unloading of catalyst or packing.
Provide vessel davits for handling items such as internals and relief valves
on vessels exceeding a height of 30 feet (9m) above the high point of the
finished surface, and on vessels not accessible by mobile crane. Orient
davits to allow the lowering of appurtenances into the access area.
Walkways
Walkways should have a 2'-6' (1m) horizontal clearance (not necessarily
in a straight
line) and headroom of 7'- 0" (2.1m)
James O. Pennock is
a former Piper with more than 45 years experience covering process plant
engineering, design, training, pipe fabrication and construction. He is
now retired and lives in Florida, USA.
© Copyright pipingdesigners.com 2004-2006 All Rights Reserved