|
Process Design Team: Thinking
outside the box
Reprint courtesy
of: HYDROCARBON PROCESSING
December 2003
Process Design Team: Thinking outside
the box
By James O. Pennock, Piper, Consultant
(Retired), Bayonet Point, Florida USA
Designing the modern process plant
is not a simple task. The typical process plant is a long, costly
and complex effort. The total project effort is normally made
up of a large diverse group of people from many disciplines. A
sophisticated firm with a highly trained and experienced staff
normally accomplishes the actual hands-on engineering and design
work. Members of the overall project group will also include the
client's team. There will be the client's project management,
the client's plant operations, and the client's maintenance group.
There are also the process licensors (if applicable), vendors,
and suppliers. Then there are the service organizations, sub-contractors,
and the construction management team. For most process plants,
there will also be present, the influence of local, state, and
federal (or national) representatives.
Each of these entities or groups will contribute their own specific
rules as codes, standards, specifications, regulations, and practices.
These rules are there for a purpose and for the most part that
purpose is safety. These rules are meant to be followed. At times'
engineers and designers may feel "boxed-in" by what
seems to be conflicting criteria. It is sometimes difficult, but
as we all know not impossible to comply with the rules. There
may be cases however, where a design team has successfully complied
with all the specific written project criteria along with all
the rules and still ended up with a poorly designed plant.
Good design is also important to a project's success. Good plant
design is not just the simple interpretation of the applicable
written criteria. Good design includes how the criteria are applied.
While it is true that the design team must know and properly apply
all the applicable codes, standards, specifications, regulations,
and practices, they must also know what constitutes good design.
'Thinking outside the box' is a phrase that is popular today.
The box, in this case is these rigid codes and standards. The
design team must be able to get outside the box and think about
those issues that are not stated in the pure terms of the written
word of the rules. These issues relate to; plant purpose and functionality,
cost verses worth, schedule, safety, constructability, operations,
maintenance, and aesthetics. Every person on the design team needs
to broaden their thinking. They need to include all aspects of
the total project. They need to 'think outside the box.'
Purpose and functionality
Process plants are designed to perform a specific function. They
will make one or more specific product. These functions and products
must also meet very specific quality and quantity specifications.
As stated before, designing and building the modern process plant
is a long, complex, and costly effort. It does not make sense
to spend three to five years and the millions (even billions)
of dollars on a project only to find out it will not fulfill its
intended purpose. Every person on the design team needs to be
fully informed of the project's purpose and function. They must
then do everything possible to insure that the finished plant
will successfully accomplish that purpose and will function the
way it is intended.
The quantity of product produced and the capacity of the plant
is also an important part of a plant's purpose and function. The
design team must insure that all equipment, piping systems, controls,
and power systems are the proper size. The finished plant must
meet the target capacity. The project team must also guard against
over design. The target capacity is normally the result of a long
study based on projected market demand. It is not prudent to end
up with a plant that produces 150% of the stated design target.
Granted, a plant's actual performance is not an exact and absolute
science. Performance that is 2%, 3%, 4%, or even 5% over the design
target would not be unreasonable. Performance that is 30%, 40%,
50%, or more means that the initial plant was grossly over designed
and cost far more than necessary. It also means that the operating
costs for years to come will be excessive. Operating costs will
be incurred for the total installed plant but the plant may now
need to operate at a greatly reduced rate based on the market.
This means the plant will not be run at peak performance.
Cost vs. worth
The issue of cost relating to a process plant is also not a one-dimensional
item. Total plant cost will include; the initial capital cost,
operating costs, insurance, taxes, and ongoing maintenance costs.
The initial capital cost is not a single facet item. Total capital
cost of a project will include front-end costs, actual project
costs, and start-up costs. The front-end costs may include moneys
for product R&D, project feasibility and funding studies,
and site acquisition. The actual project costs will include the
site development, licenses and permits, front-end engineering,
detailed engineering, production engineering, capital equipment
procurement, bulk material procurement, construction, testing,
and validation. The start-up costs will include the hiring and
training of staff, day to day operations, and maintenance. Some
project cost items are going to be what they are going to be no
matter what the design team does. Among the fixed costs are building
permit fees, licenses fees, taxes, payroll burdens, and insurance.
The project team will go through the process of developing estimates
and fixing a target budget for each cost area. The team will then
endeavor to stick to the budget by following all the normal practices.
Selecting the 'low bidder' is one example of these normal practices.
Selecting the low bidder is not in itself always a bad thing.
However, it may not always be a good thing. Rigidly selecting
the low bidder who is not qualified or not proven may not be the
most cost-effective answer for the overall project. There are
all sorts of other examples that could be cited but the low bidder
is one of the most visible and recognizable. The team needs to
have a neutral, objective, and rapid method to measure all cost
oriented decisions. They need to have a method of measuring what
a decision will cost against what the decision is worth.
What is the decision worth and how does the team establish it?
One method that has been used in the past is based on the loss
of production and return on investment. With this method, the
value of the daily production established for the finished plant
is adopted as the worth factor. This worth factor is published
to the design team. Some clients may consider the real monetary
return to be a highly confidential number. OK! Establish a hypothetical
but logical number for use by the project. The number needs to
be published to all the key discipline, middle and upper management
personnel on the project. A small project from my past had a stated
projected daily revenue return of $160,000 per day. I do not know
if this was the real number or if it was a hypothetical number
created for the project. The fact that the number was real or
made-up did not matter, the project team had a number. It was
printed out in big numbers and posted in the conference room and
all the key work areas. When we were faced with a cost decision
that could take more time, we would balance the cost in question
against the $160,000 per day number.
A hypothetical example of this might be the selection of the successful
bidder for a major and critical piece of equipment. The low bidder
is $50,000 under the next or second lowest bidder. The second
lowest bidder has more reliable track record and can meet the
project's tight schedule. The low bidder however, wants additional
time added to the overall manufacturing and delivery schedule.
This extra time will delay the plant start-up by at least one
week. Use the $160,000 figure and you do the math on this one.
Timing of the project is also an important and complex issue.
One or more of the products of the plant may be market driven
and if the plant is not finished on time then that revenue is
lost. Even worse, the late project completion of the plant could
cause the loss of the intended customer for that product. The
project could be driven by EPA criteria with stiff monetary penalties
for non-compliance. Even if not driven by the market or environmental
compliance, there is always labor cost as the motivation to finish
on schedule. The longer a project takes the more it will cost
and the longer the wait for any return on investment. The 'loss
of production' comparison will also apply here.
Schedule
Job scheduling is both an art and a science. There are people
who are absolutely not capable of generating a schedule for fixing
even the evening's dinner let alone a schedule for a complex process
plant project. There are also others who seem to be able to visualize
the schedule as if it were a movie playing out in their head.
Schedules are absolutely mandatory for complex process plant projects
of any size. It's the old saying, "If you fail to plan, then
you plan to fail." Schedules are part of the plan and they
have four distinct phases. There is the schedule development phase.
There is the phase normally recognized as schedule execution.
There is, of course, that phase known as schedule maintenance.
The fourth phase is the one that is often overlooked. This is
the phase of schedule assessment.
During the schedule development phase there are many things that
must be considered in order to improve or accelerate a project
schedule. All intra- and inter-discipline activities and task
areas must be looked at for proper sequencing. Opportunities for
schedule improvement can often be found in areas related to these
interdisciplinary activities and tasks. Every effort should be
made to find opportunities and methods that result in a shorter
schedule and a more viable master plan.
The schedule execution phase is in fact the execution of the plan.
Here the team must remember to keep the plan in front of them
and visible. Making a plan and then putting it in the file cabinet
does not make sense. The schedule was also intended as a guide,
to be used and to be beaten whenever possible.
As activities and tasks are completed the schedule should be updated.
This is the maintenance phase. Also as the project develops things
will change, not everything will run as smoothly as planned. The
schedule must be periodically reevaluated, modified and updated
to fit the new reality.
Schedule assessment phase should have three types of meetings
and should be a part of every project. The three types of schedule
assessment meetings may be called many things but are basically
'developmental', 'periodic' and 'emergency.' The (one or more)
developmental assessment meetings will be held as the schedule
is being prepared during the early stages of the project. All
discipline leaders should participate in these meetings. The periodic
schedule assessment meetings are also attended by the discipline
leaders and should be held at least once a month to review status
and correct the course as required. The emergency schedule assessment
meeting is held, on an as-need basis, when there is a major event
that causes peril to the project. When this happens, every member
of the team needs to adopt the attitude of "What can I do."
At the end of the project there should be a review of the schedule
by the project team to evaluate how they did and what they could
do better next time.
Safety
This is, and will always remain, a primary issue in the design
of any process plant project. Safety must be a part of the thinking
of every person on the project during every activity and every
task. Some may say that safety is an issue that only impacts the
field during construction or the finished plant during operations
and maintenance activities. This is just not so. The design team,
by the choices they make, will either design a plant that is safe
or they will design a plant that is unsafe. This issue is something
like "Humpty-Dumpty." Once its done wrong you cannot
put it right again. The safety of the plant operators and the
other plant personnel must be thought about at all times during
the design phase. The people who will operate and maintain a process
plant will spend much of their lives there. They may work five,
six, or sometimes even seven days a week, week after week, year
after year. They deserve to feel safe while they are in their
work area.
Yes! All plants have some degree of danger. On the other hand
plants that are properly designed will be safer. Safe plants are
well organized with straight well defined routes of access and
escape. Safe plants have proper headroom. Safe plants have all
critical operating valves and controls properly marked and easy
to reach. Safe plants have the emergency shut-off or shutdown
controls located in a logical place. Safe plants are easy to keep
clean. Safety is designed in, not added on later.
Constructability
Is it possible to design something that cannot be built? This
is an interesting question and the answer is both no and yes.
Some people might say "No," it is possible to build
anything. From a pure technical standpoint there may be no limit
to what can be built. However, every project has its limitations
and we are not addressing the technical aspects of building something.
What we must address here is the non-technical aspects of budget
and schedule. The answer then, may be yes, if you have a limited
budget and deadline or restrictions on time. If the plant cannot
be build within the predefined budget and schedule limits then
the project is not constructible. Every member of the project
team must know what the budget and schedule constraints are. They
must also be aware of what effect they and their decisions have
on those limits.
Operations
If the operators do not like it (the new plant) they may make
sure it does not work. This is a strong statement, but human nature
being what it is there could be some degree of truth in it. During
the design stage, choices will be made in the location of key
control and sample points. It is wise to talk to the operations
team and find out what they are thinking. What do they consider
good when it comes to operations and what they consider as bad?
Remember that these people are going to live (in shifts) in this
plant twenty-four hours a day, every day, for years. Do not set
it up so they spend their days grumbling about the way you did
your job. Every member of the design team should be given the
opportunity to visit an operating plant. They should talk with
operators and listen to both their comments and complaints.
I remember a project where there were four reactors each requiring
extensive operating manifolds and multiple test points. A previous
design had the reactors spread out and located some distance from
each other. It also had the operators climbing up and down the
four reactors to access all the required operating valves and
sample points. After discussions with the operators, the new project
took the approach that the plant would work better if the plant
operators had a better arrangement for the work. The four reactors
in the new plant were grouped together and all the operating valves
and sample points were located at grade for easy access by the
operators.
Maintenance
Here is another important aspect of the plant design process.
If you get this wrong, it's one you cannot easily fix. If a plant
is not maintained it will not function properly, it will not be
productive, and it will not make the intended quality and quantity
of product. If it is not productive it will not be economical
to run and will soon be shut down.
The maintenance needs for the general types of equipment such
as pumps, exchangers, vessels and tanks are fairly well known.
All designers with the training and the right experience will
have an understanding of maintenance for these items. However,
there are three things we need to do to help when it comes to
maintenance.
First, we need to understand the maintenance philosophy for the
plant. The maintenance philosophy may be built-in, portable or
a combination. A built-in maintenance philosophy means monorails
and bridge cranes to handle the removal or installation of equipment
or parts. A portable maintenance philosophy means that all equipment
and part removal will be accomplished using mobile cranes or a
forklift.
Second we need to do our homework when it comes to the equipment
specific to "this" project. Is there any new or different
about the equipment on this project? If so then go ask questions
and find out what are the maintenance needs and how this maintenance
will be handled.
Third, we need to insure that the project maintenance philosophy
is carried-out relative to every piece of equipment. This means
that all the design groups (piping, structural, electrical, instrumentation,
etc.) do not obstruct the required maintenance access.
Aesthetics
Some will ask what does aesthetics have to do with good process
plant design? Looking good does not have anything to do with process
plant purpose and functionality. Looking good does not have anything
to do with process plant operation, maintenance or constructability.
However, the client/owner wants a plant that looks as it was designed
and built by professionals. We have all seen plants that were
real eyesores and we have also seen plants that are almost pretty.
Many of these pretty plants show up on the covers of our trade
magazines.
There are a number of small, simple things that can be done to
improve the overall appearance of the plant. Try to line up like
things in an organized manner. Try to establish some symmetry
in the placement of objects. One simple example is to place all
the stairways for the storage tanks in the same quadrant.
Most likely you will not live next door to a plant or drive by
one every day to and from your work but other people do. It is
not unreasonable or hard to give some thought to what a plant
will look like from outside the fence. We should take pride in
our work, pride in the design and make our company proud and the
client happy.
The items listed above are not specifically addressed in our codes
or standards for the design of a process plant. They are outside
the box, however they should be considered very important to the
success of any project.
James O. Pennock has more than forty-five years in the process
plant design profession. He has been involved in both home office
and job site assignments on refinery, chemical, petrochemical,
power and other projects. His experience ranges from entry level
designer to engineering manager. Much of this was with Fluor.
He is also the author of the book "Piping Engineering Leadership
for Process Plant Projects." He is now retired, living in
Florida, USA and does only occasional consulting work.
Mr. Pennock can be contacted
via E-Mail at jopennock@netscape.net.
|